You are here:
Estimated reading time: 1 min
Project Abstract:
The overall objective of this research is to improve the guidelines for the modeling, design, and construction of integral abutment bridges (IABs) by completing the following tasks:

Task 1: (Literature review and gathering of information)  

Task 2: (Improve guidelines for the modeling, design, and construction of IABs)

Based on the input from a number of state DOTs (Mass, Vermont, and Maine), the following tasks has been undertaken:
(a) A study of the effect of the roadway profile grade on substructure; 
(b)A study of the constructibility of pile supported IABs at a site with shallow bedrock;
(c) A study of the effect of range span and of skew angle on axial and bending stresses in the superstructure and substructure;
(d) Improve the finiteā€“element modeling and analysis of IABs.   

Task 3: (General Guideline) Provide a final report regarding the topics studied.

Principal Investigator:
Dr. Susan Faraji

Institution:
University of Massachusetts Lowell

Project Type:
Base-Funded Research

Start Date:
9/1/2018

Project Cost:
$125,625

Project Status:
In Progress

End Date:
9/30/2023

Agency ID:
69A3551847101

Sponsors:
University Transportation Centers Program, Department of Transportation
University of Massachusetts Lowell


Implementation of Research Outcomes:
This project is in its initial research phase. Implementation of Research outcomes will be reported upon completion of initial research.

Impacts and Benefits of Implementation:
This project is in its initial research phase. Impacts and benefits of the research will be reported after the implementation phase.

Related Links:
https://www.uml.edu/Research/tidc/faculty-staff/


Downloadable Documents

Printable Project Information Sheet

April 2019 Semi-Annual Progress Report

May 2019 Bi-Monthly Progress Report

July 2019 Bi-Monthly Progress Report

September 2019 Semi-Annual Progress Report

December 2019 Quarterly Progress Report

March 2020 Quarterly Progress Report

June 2020 Quarterly Progress Report

September 2020 Quarterly Progress Report

December 2020 Quarterly Progress Report

March 2021 Quarterly Progress Report

June 2021 Quarterly Progress Report

September 2021 Quarterly Progress Report

December 2021 Quarterly Progress Report

Tags:
Views: 65
Categories: